Eskom’s boiler contractor Hitachi defends its reputation

Johannesburg - Eskom’s boiler works contractor at Medupi and Kusile has moved to defend its reputation, and to clarify its position in respect of any perceived non-performances in meeting its contractual obligations to deliver steam of the right cleanliness, speed, temperature, pressure and mass flow-rate to the turbines at the power station construction sites.

At a briefing on 23 January 2015, David Milner, responsible for business development and corporate communications at Mitsubishi Hitachi Power Systems Africa (MHPSA) (formerly known as Hitachi Power Africa), refuted any suggestions that the company had incorrectly designed the temporary pipework for blow-through testing at Medupi.

On the contrary, Milner indicated that the temporary pipework for blow-through testing had been correctly designed to meet the steam conditions specified by Eskom for blow-through testing of  both the high pressure and intermediate pressure pipework systems of Unit 6 at Medupi (the first unit to be commissioned).

Contractual requirements met

Milner also gave the assurance that, for the high-pressure system, the required levels of steam cleanliness, as measured by the number and diameter of indentations in a defined area on a target plate installed in the temporary blow-through piping, met the contractual requirements specified by Eskom in its contract with MHPSA. He said the company was on the way to achieving these requirements on the intermediate pressure system when the blow-through testing was stopped by Eskom.

Steam blow-through is conducted after chemical cleaning to blow steam through the boiler and associated pipework in order to clean the plant of construction debris, particles, scale and other contaminants, and establish and prove the required steam inlet conditions before connecting the final piping to the steam valve and turbine.

Eskom contractual specifications set out the required steam speed, steam turbulence factor and steam mass flow-rate to be used during the blow-through process, where conditions are far more severe than during normal full-load operation. MHPSA says it met all such contractual requirements on the high pressure system.

Watch:


The first oil fire of unit 6 at Medupi power station project on October 22, 2014.


It would appear that the problems reported by Eskom in achieving the required levels of steam cleanliness at the specified steam speed, turbulence and flow rate conditions during blow-through testing are the result of some “disconnect” between Eskom’s contractual specifications with its boiler works contractor (MHPSA) and its turbine works contractor (Alstom).

Understanding the disconnect

Part of this disconnect relates to the actual point of measurement of steam speed, with MHPSA indicating that its contract with Eskom clearly states this should be at the target plate within the steam pipe, where the pipe cross-sectional area is somewhat reduced due to the target plate itself. MHSPA says that if the steam speed is measured at a position away from the target plate, where the pipe cross-sectional area is greater, the steam speed would be lower. The measurement procedure used, says MHPA, was not in accordance with its contract with Eskom.

MHPSA says that, at the target plate, the steam speed was above the 200 meters per second required in its contract with Eskom. Measured elsewhere in the pipe, the steam speed would have been around 180 metres per second, and this is what has led to pubic confusion around the issue.

A further disconnect between the boiler and turbine steam quality specifications relates to the way in which the steam contaminant particle size diameter is calculated from indentations in the target plate after blow-through. As a result of particles striking the target plate at various angles, some indentations are elliptical and not circular, and in these cases MHPSA suggests that various methods can be used to calculate the contaminant particle sizes in the steam during blow-through testing.

The final area of confusion  between the boiler and turbine steam quality specifications relates to the area size on the target plate within which a count is done on the number of contaminant indentations after blow-through testing. The area size is specified in MHPSA’s contract, but a larger target plate area for the count would obviously affect the number of indentations measured.

Delays cause fuel costs

While the issues detailed above are indeed somewhat technical and obscure, the outcome of the delays in completion and contractual acceptance of the blow-through test results have already caused significant additional fuel oil costs to fire the boiler during the extended blow-through testing period.

The seven to nine-week delay in first synchronisation of Unit 6 at Medupi, due to the extended blow-through and other issues not related to MHPSA, could also result in additional open cycle gas turbine (OCGT) diesel costs being incurred by Eskom.

Eskom has indicated that it spends R1bn to R2bn per month on diesel to run the OCGTs in the Western Cape.

Management changes

Mitsubishi Hitachi Power Systems Africa, based in Johannesburg, recently announced management changes in which Eitaro Takayama was appointed executive chairman and Toshinori Shigenaka CEO on 1 December 2014. Hirosumi Sometani becomes chief commercial officer, while Shiro Ishise becomes executive director, projects.

The changes were announced by Takato Nishizawa, president and CEO of the Japanese parent company, Mitsubishi Hitachi Power Systems, and reflect an increased role within the South African operation by its Japanese management and technical staff. The company was formed in February 2014, integrating the global thermal power generation systems businesses of Mitsubishi Heavy Industries (MHI) and Hitachi.

The new South African subsidiary, Mitsubishi Hitachi Power Systems Africa, is part of the merged Mitsubishi/Hitachi entity, and took over the Medupi and Kusile boiler contracts awarded to Hitachi Power Africa.

Mitsubishi Hitachi Power Systems Japan became the majority shareholder in the South African operation in October 2014, acquiring the 75% shareholding previously held by Mitsubishi Hitachi Power Systems Europe.

The remaining 25% is held by a Black Economic Empowerment (BEE) partner, Kagosano NPC, a special purpose BEE vehicle set up to replace the 25% financial interest in Hitachi Power Africa formerly held by ANC investment company, Chancellor House.

* This story first appeared on www.ee.co.za

* Chris Yelland is the MD and an investigative journalist at EE Publishers.

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Voting Booth
Do you think corruption-accused National Assembly Speaker Nosiviwe Mapisa-Nqakula will survive a motion of no confidence against her?
Please select an option Oops! Something went wrong, please try again later.
Results
No, her days are numbered
41% - 500 votes
Yes, the ANC caucus will protect her
59% - 710 votes
Vote
Rand - Dollar
18.90
+0.2%
Rand - Pound
23.86
+0.2%
Rand - Euro
20.36
+0.3%
Rand - Aus dollar
12.31
+0.3%
Rand - Yen
0.12
+0.2%
Platinum
908.05
0.0%
Palladium
1,014.94
0.0%
Gold
2,232.75
-0.0%
Silver
24.95
-0.1%
Brent Crude
87.00
+1.8%
Top 40
68,346
0.0%
All Share
74,536
0.0%
Resource 10
57,251
0.0%
Industrial 25
103,936
0.0%
Financial 15
16,502
0.0%
All JSE data delayed by at least 15 minutes Iress logo
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE