Nkandla landscaping cost R16m

Jeff Wicks, The Witness

Durban - Architect Minenhle Makhanya built a garden fit for a king - eventually spending more than R16m on landscaping at President Jacob Zuma's home.

This has emerged from reams of official Department of Public Works (DPW) documents made public in pursuit of Zuma’s personal architect Makhanya.

Designing a garden fit for Zuma blossomed out of control.

Indigenous plants

Landscaping the grounds of the Zuma family’s sprawling Nkandla compound rose exponentially, with contractors importing protected indigenous trees and plants from across the country.

In its completion phase, the plush presidential pad now looks part of the natural bush hillscape.

The embattled architect has been slapped with the mammoth R155m bill for his alleged inflation of the cost of the compound.

The documents were filed in response to Makhanya’s intention to oppose the lawsuit, which came after months of mounting political and public pressure.

The flourishing cost of carefully designed indigenous gardens, manicured lawns and lush swathes of rehabilitated veld has been a point of focus in the graft-busting Specialised Investigating Unit’s report into the upgrades at the president’s compound.

Costs split

According to DPW cost-allocation documents from 2011, over R16m had been set aside for landscaping of the president’s home.

The bill was to be split between the public and private purse of the first citizen, although it is unclear how much of this bill has been settled.

Bonelena Construction and Moneymine CC scored big with the landscaping contract - the bulk of the business shared between the two.

Both companies were identified in Public Protector Thuli Madonsela's report into the upgrade of the homestead titled Secure in Comfort.

They found their way into the spotlight for unduly benefiting from inflated fees.

According to the documents submitted by landscape architects, large tracts of land had to be redesigned because of “new security measures”.

Cycads, fully grown trees

“The overall finished landscape is natural veld, enhanced with shrubs and trees and is not a manicured landscape,” the papers read. Among the enhancements are 12 protected cycads, which were brought in complete with tracking tags and papers for the landscaping project at a cost of R5 500 each.

Fully grown trees at R7 500 each were also shipped to the rural hamlet and strategically placed for “secrecy”. The total cost for trees came to R1.6m.

No expense was spared in the establishment of feature gardens and ambience; with a proposed spend of hundreds of thousands of rands for recessed lighting which would “enhance the estate”.

One of the feature gardens made of up indigenous succulents and shrubs, set in front of the military-run clinic, came with a price tag of R30 000.

Rehabilitation of surrounding land disturbed during construction of the homestead cost almost R2.5m.

Attempts by The Witness to contact Bonelena Construction and Moneymine CC were unsuccessful.

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Voting Booth
Do airplane mishaps have any effect on which airline you book your flights with?
Please select an option Oops! Something went wrong, please try again later.
Results
No, these things happen. I pick based on price
49% - 857 votes
Yes, my safety matters. I don't take any chances
51% - 896 votes
Vote
Rand - Dollar
19.17
-0.3%
Rand - Pound
23.84
-0.2%
Rand - Euro
20.48
-0.1%
Rand - Aus dollar
12.45
-0.5%
Rand - Yen
0.12
-0.2%
Platinum
920.20
+0.0%
Palladium
1,023.50
-0.2%
Gold
2,315.99
-0.3%
Silver
27.13
-0.6%
Brent Crude
88.42
+1.6%
Top 40
68,425
+0.6%
All Share
74,397
+0.5%
Resource 10
59,627
+0.0%
Industrial 25
103,976
+1.1%
Financial 15
15,911
+0.1%
All JSE data delayed by at least 15 minutes Iress logo
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE