Share

Glossary of terms to assist understanding of Eskom key performance indicators

accreditation
0:00
play article
Subscribers can listen to this article
The Eskom Files is an ongoing investigation by News24.
The Eskom Files is an ongoing investigation by News24.
News24

As part of News24's reporting on The Eskom Files, an extensive data investigation into key performance metrics used by Eskom was undertaken. This glossary is intended to assist readers in understanding some of the terms. 

Energy Availability Factor

The overall measure of Eskom generation performance. It is calculated by taking the total theoretically possible generation capacity over a given time period (100%) and deducting the "losses" incurred as a result of generation units being offline for PCLF, UCLF and OCLF (explained below). A more general description is that EAF represents the electricity that was available to be generated

Installed Capacity

This refers to the total, theoretical generation capacity (usually calculated in megawatt-hours - MWh) that an electricity generation unit has. This is calculated as follows:

There are 720 hours in a 30-day month. A 500MW generation unit therefore has an installed capacity of 360 000 MWh in that same month (500MW x 720 hours).

(A unit refers to the machinery associated with one turbine that generates power.)

Planned Capability Loss Factor – PCLF

This is the amount of time generation units were taken offline for planned outages – being planned repairs or maintenance – and is calculated as a percentage of the total installed capacity over the same time frame.

Unplanned Capability Loss Factor – UCLF

This is the amount of time generation units were taken offline for unplanned outages – being unplanned repairs or maintenance – and is calculated as a percentage of the total installed capacity over the same time frame. UCLF also includes Partial Load Losses, explained below.

Operational Capability Loss Factor - OCLF

This is the amount of time generation units were taken offline for outages caused by things that are outside of the unit’s manager’s control and is calculated as a percentage of the total installed capacity over the same time frame.

Outages

UCLF, PCLF and OCLF are also commonly referred to as outages simply meaning the unit was out of service.

Full Load Loss

This is when an entire unit is offline as a result of any factor that resulted in the unit being unable to run. 

Partial Load Loss

This is when a unit is run at below optimal levels usually as a result of a fault that requires the unit to be run at lower speed, or load, either because the fault results in the unit being unable to run at higher load, or because running the unit at full load with the fault could result in the unit breaking down.

Generation Load Factor – GLF

This is an indication of how hard a unit is working. It is a percentage of the actual MWh produced compared to the total installed capacity over the same time frame. A 500MW unit that produced 234 000 MWh in a 30-day month, or over 720 hours, will have a generation load factor of 65%.

Energy Utilisation Factor – EUF

EUF is the most useful performance metric and is similar to GLF, but it also considers EAF. Simplistically, EUF is the generation load factor during the periods when the unit was available.

For example: A 500 MW unit can, theoretically, produce 360 000 MWh in a 30-day month. If planned maintenance is done for 5 days, this will result in PCLF of 16.67% because 60 000 MWh were ‘lost’. Then the unit breaks, leading to a repair that takes 48 hours, or two days. This will result in 6.67% of UCLF, because 24 000 MWh was ‘lost’. The unit produces 234 000 MWh in the same month. That means the unit had a generation load factor of 65%, and an EAF of 76.6% (100% - PCLF – UCLF -OCLF). The unit had no OCLF for this month.

The EUF for the month for the unit then is calculated as a percentage: GLF divided by EAF x 100. The unit then had an EUF of 84% for the month.

An EUF above 80% is not ideal for coal fired power stations and it shows the units at the power station were run harder than what is advisable.

Cold reserve

This is when a unit is not running because it is not needed. Eskom rules state however that if a unit is placed under cold reserve, the power station must be able to bring the unit back online within a stipulated time frame in case its needed, referred to as call up time. If a unit is placed under Avalailabe Cold Reserve, or AVCR, no work may be done on the unit.

Opportunity Maintenance during Operation - OMOR

This is when work is done on a unit while it is still running. The most common example of this is when a set of coal mills (which grind the coal into fine dust) is taken offline to be fixed while the remaining mills are used to keep up with the coal being supplied to the boiler.

Opportunity Maintenance during Cold Reserve - OMCR

This is when opportunity maintenance is undertaken on units while they are in cold reserve. The work is not allowed to be so significant that could affect its ability to come back online within the call up time may be done.

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Voting Booth
Are you among the many South Africans who've added more tinned fish to their grocery baskets?
Please select an option Oops! Something went wrong, please try again later.
Results
Yes, pilchards is the new chicken
34% - 80 votes
No, I can't stand canned foods
66% - 158 votes
Vote
Rand - Dollar
18.55
-0.2%
Rand - Pound
23.16
+0.0%
Rand - Euro
19.92
-0.0%
Rand - Aus dollar
12.20
+0.1%
Rand - Yen
0.12
+0.1%
Platinum
977.40
-0.2%
Palladium
973.50
-0.1%
Gold
2,318.48
+0.2%
Silver
27.38
+0.5%
Brent Crude
83.16
-0.2%
Top 40
70,790
0.0%
All Share
76,930
0.0%
Resource 10
61,038
0.0%
Industrial 25
107,159
0.0%
Financial 15
16,711
0.0%
All JSE data delayed by at least 15 minutes Iress logo
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE