Noordkaap Bulletin
Share

Intervention in Kimberley’s bulk water supply showing results

accreditation
0:00
play article
Subscribers can listen to this article

An intervention to address critical maintenance of Kimberley’s bulk water supply infrastructure is underway, and three contracts with a total construction value of R88,26 million have been awarded up until now.

Years of poor maintenance combined with technical and mechanical challenges at the old and new water treatment plants at Riverton next to the Vaal River from where Kimberley gets its water, are main reasons for these plants being dysfunctional and not being able to purify and pump water at full capacity.

As part of the extensive maintenance process, water supply interruptions in the coming months are inevitable, said Rikus Rossouw, engineer at Bigen Africa.

“It will hurt; it will hurt more than now,” he remarks, referring to the inevitable water shutdowns.

Currently, Kimberley residents and businesses are subjected to nightly water shutdowns, as well as sporadic water shutdowns during the afternoon. In recent months unannounced water shutdowns took place, leaving residents with dry taps for days on end.

Filters, pumps dysfunctional

During a special media visit to the old and new plant on Wednesday, 6 March, Rossouw says the old plant can be functional within a couple of weeks.

The full functionality of the old plant is needed since much of the maintenance needed at the new plant will require a full water-shutdown.

The first part of the old plant, with six filters, came into operation in December 1949, and the second part with another six filters, in October 1962. Rossouw described this plant as “a magnificent infrastructure and building”.

The old Riverton Water Treatment Plant is described as a “magnificent infrastructure and building”. Its first section was opened in December 1949, and the second in October 1962.
The first section of the old plant at Riverton was officially opened on 7 December 1949.
Old instrumentation and museum-like paraphernalia in a neglected glass display case in the main entrance of the old plant at Riverton.

Last week, during the media visit, only six of these 12 filters were working, and of the six pumps, only three were operational.

Parts that were moved from one piece of equipment to another, instead of replacing a defective part, contributed to the situation.

Rikus Rossouw, engineer of Bigen Africa, explaining the functioning of the old water plant. Parts that were moved from one piece of equipment to another, instead of replacing a defect part, contributed to the poor functionality of the plants.

A high-lift pump station next to the old plant, which pumps water into the bulk supply system, was built around 2018 and is state of the art. However, the power supply to this pump station was never sufficient, and upgrading to bulk power supply will be done. At the time of the media visit, the pump station was operating on half capacity.

Work will be undertaken at this high-lift pump station built around 2018, which is apparently only working at half capacity.
Part of the modern high-lift pump station, built in 2018.

At the new plant, raw water from the river is mixed with chemicals in the three rapid mixing chambers for the pre-chlorination process to take place.

It is said that the pre-chlorination process has not been working for approximately 12 years; Bigen Africa commenced with work at the new plant in October, and in January the pre-chlorination process was up and running.

One of the clarifiers at the new plant, which is cone-shaped. In the clarifiers, the sludge is scraped away with rotating scraper blades.

Part of the new plant are 24 high-performance filters: with only six operational during the media visit.

In November algae in the water was a huge problem; filters needed to be washed and cleaned more than usual, which used plenty of already treated water.

Replacing the filter media in the filters is the first step in cleaning it and assisting in optimising its functionality.

The working of these filters at the old and new plant can be described as similar to that of a swimming pool, in which sand has to be replaced from time to time. The filters at the plants, however, are the size of a medium to large swimming pool.

Some of the filters at the new plant. Replacing the filter media (sand) in these filters was part of the process to recover functionality.

Planned shut downs, when possible

Wherever possible, maintenance is executed without a water-shutdown. Also, as far as possible, water-shutdowns will be planned and communicated, said Thapelo Matlala, municipal manager of the Sol Plaatje Municipality.

However, situations such as a major leak at Midstation in the vicinity of the 3 South African Infantry Battalion (3 SAI) at Roodepan might be a reason for an unplanned and urgent water-shutdown in the near future.

Rossouw says a gasket on this bulk water supply line started leaking in December 2023. When a valve was replaced in November in the same chamber, the gasket was not yet leaking. According to Rossouw, it is common for a gasket to perish with time.

To replace this gasket, a full water-shutdown will be needed. Drying the system, replacing the gasket, and refilling the system with water can take days, he says.

Fixing a major leak at the new high-lift pump station was undertaken during the media visit. It was aimed to fix this leak without shutting down the water supply.

Thirty-five projects planned

In a statement dated 6 March, Matlala provided more insight in the roll-out of the Budget Facility for Infrastructure Programme (BFI) to address critical maintenance on the municipality’s bulk water supply infrastructure.

As part of this roll-out, 35 projects are planned to reverse the water challenges through the R2,5 billion National Treasury BFI grant over the next seven years.

The three contracts that have been awarded so far are firstly for emergency meter installation, flow and quality monitoring; secondly for emergency leak repairs on priority leaks identified from the SmartBall survey; and thirdly, the fixing of the chlorine, chemical dosing, instrumentation and control at the new plant.

A screenshot of the media statement from the Sol Plaatje Municipality on 6 March, providing more detail on the three contracts provided.
More detail provided by the Sol Plaatje Municipality on five more projects, of which two will be awarded on Friday, 15 March, with three others at a tender stage.

Matlala indicated that site handover of all three these contracts has been completed and construction begun, with three major leaks having already been attended to by the appointed contractor for emergency leak repairs.

A further two projects will be awarded by 15 March, with three others at a tender stage.

Water production already improved

Matlala provided an update on the recent work being carried out at the Riverton Water Treatment Plant to improve water production:

Work to put two dysfunctional clarifiers at the old treatment plant back into production has commenced. The cleaning of one of the clarifiers has been completed. Valves were repaired and tested, and it was estimated that the commissioning of this clarifier will be completed on Friday, 8 March.

During the media visit this clarifier at the old plant was cleaned and faulty valves replaced. It is important for the desludge process to be effective in these clarifiers, or else the filters will fail due to the extreme load of sludge.
A clarifier at the old plant that was already cleaned.

The second clarifier is undergoing cleaning and the valves have been repaired. Once functional, these two clarifiers will improve water production by 15 megalitres per day.

The filter media on two filter bays at the new plant has been replaced to improve the filtration process and overall water production capacity.

Matlala said support is still being provided by the Bigen Africa team, as well as the Kimberley-based Ekapa Mining, who have as previously reported, committed funding of R10 million towards efforts to address the water challenges.

“There is no quick fix, but we are not stopping. Everyday small things to improve production and quality of water, are fixed. We are seeing progress,” remarks Jihaad Suliman of Bigen Africa.

We live in a world where facts and fiction get blurred
Who we choose to trust can have a profound impact on our lives. Join thousands of devoted South Africans who look to News24 to bring them news they can trust every day. As we celebrate 25 years, become a News24 subscriber as we strive to keep you informed, inspired and empowered.
Join News24 today
heading
description
username
Show Comments ()
Voting Booth
Should the Proteas pick Faf du Plessis for the T20 World Cup in West Indies and the United States in June?
Please select an option Oops! Something went wrong, please try again later.
Results
Yes! Faf still has a lot to give ...
69% - 1683 votes
No! It's time to move on ...
31% - 771 votes
Vote
Rand - Dollar
18.70
-0.4%
Rand - Pound
23.46
-0.2%
Rand - Euro
20.01
-0.2%
Rand - Aus dollar
12.20
+0.3%
Rand - Yen
0.12
+0.0%
Platinum
945.40
-1.5%
Palladium
955.50
-2.5%
Gold
2,311.87
-1.0%
Silver
26.57
-2.1%
Brent Crude
88.40
-1.2%
Top 40
70,277
-0.2%
All Share
76,416
-0.1%
Resource 10
62,415
-2.5%
Industrial 25
105,132
+0.5%
Financial 15
16,577
+0.9%
All JSE data delayed by at least 15 minutes Iress logo
Editorial feedback and complaints

Contact the public editor with feedback for our journalists, complaints, queries or suggestions about articles on News24.

LEARN MORE